Estimates and cost review
Conceptual estimates for the configured home: line-item costs, assumptions, exports, and regeneration history.
Configure a home
Loading configurator…
Conceptual cost
Takeoffs and line costs
| Line | Takeoff qty | Basis unit | Derived unit cost | Confidence |
|---|
| Line | Cost code | Qty | Unit | Unit cost | Calculated | Effective | Override | Markers | Src rev | Trace |
|---|
Select Inspect on a line to open its source trace and override drawer.
Measured takeoff (planning-grade)
Envelope- and convention-based home takeoff: envelope/wall/roof/opening/drywall categories from the declared plan envelope; lot area measured from the lot polygon when present. Framing = plane areas. Elevations and options carry no geometry → honestly absent.
| Category | Quantity | Unit | Basis |
|---|---|---|---|
| Windows | 10 | ea | assumed |
| Exterior man doors | 3 | ea | assumed |
| Overhead (garage) doors | 1 | ea | assumed |
| Total opening area | 295 | sf | assumed |
| Envelope footprint | 2,856 | sf | derived |
| Foundation slab | 2,856 | sf | assumed |
| Exterior wall perimeter (per plate) | 220 | lf | derived |
| Exterior wall length (all plates) | 440 | lf | derived |
| Gross exterior wall area | 4,620 | sf | assumed |
| Wall framing area (plane) | 4,620 | sf | assumed |
| Siding (net of openings) | 4,325 | sf | assumed |
| Exterior wall drywall (net of openings) | 4,325 | sf | assumed |
| Roof area | 3,193 | sf | assumed |
| Roof framing area (plane) | 3,193 | sf | assumed |
| Conditioned floor area | 1,800 | sf | derived |
| Ceiling drywall | 1,800 | sf | derived |
| Interior partition drywall | 3,600 | sf | assumed |
| Elevated floor framing area (plane) | 900 | sf | derived |
- openingSchedule: SFD_OPENING_CONVENTION — Declared schematic opening convention (2/bed + 4 common windows; front/rear/garage-house man doors; overhead per garage type) — not a door/window schedule.
- foundationType: slab_on_grade — Slab-on-grade; no footings, thickening, or slab thickness modeled.
- floorToFloorFt: 10.5 — STORY_HEIGHT_FT (scheme-model3d.mjs) — the massing convention shared with 3D so takeoff and massing never disagree; not a designed section.
- roofPitch: 6:12 — SFD_ROOF_PITCH 6:12 -> plan slope factor 1.118; pitch is not modeled on catalog plans.
- partitionDrywallFactor: 2 — Both faces of interior partitions over conditioned area; declared factor, not a measured partition takeoff.
- Planning-grade, not bid-grade: NOT purchasable, bid-level, or distributor-quote output — no SKUs, no waste factors, no supplier mapping (full-product-requirements.md §2.9).
- Framing quantities are PLANE AREAS, not member counts or structural design.
- Openings are a DECLARED schematic convention, not a door/window schedule; catalog-plan quantities are envelope- and convention-based, declared per quantity.
- Moves NO money: line items, contingency/escalation, summaries, exports, and CSV columns are byte-identical.
- Not a quantity survey, appraisal, or permit determination; drawings remain non-permit-ready.
The cockpit dock TAKEOFF group (scheme-level measured quantities on the Site Studio) is staged for v1.1. The live scheme takeoff is already available to agents and operators through the guarded scheme API.
Material schedule (planning-grade)
Quote-ready material lines mapped from the measured takeoff and the org material catalog. Base is the converted takeoff quantity; waste is shown as its own component; purchase is base plus waste. Cost bases are the builder’s manual planning figures and are margin-visible only.
| Material | Base | Waste | Purchase | Order | Basis | Unit cost | Extended |
|---|---|---|---|---|---|---|---|
| WIN-V-3x4 · Vinyl window 3'x4' from: windowCountEa | 10 ea | 0% · 0 | 10 | 10 pack-rounded | assumed | $285 | $2,850 |
| DR-EXT-3x7 · Exterior door 3'x7' from: exteriorDoorCountEa | 3 ea | 0% · 0 | 3 | 3 pack-rounded | assumed | $450 | $1,350 |
| OHD-16x7 · Overhead door 16'x7' from: overheadDoorCountEa | 1 ea | 0% · 0 | 1 | 1 pack-rounded | assumed | $1,200 | $1,200 |
| RM-3000 · Ready-mix concrete 3000 psi from: foundationSlabSf 4.0 in slab: (4/12) ft ÷ 27 = 1/81 cy per sf | 35.3 cy | 5% · 1.8 | 37 | 37 | assumed | $185 | $6,849.11 |
| FR-WALL · Wall framing package from: wallFramingAreaSf | 4,620 sf | 10% · 462 | 5,082 | 5,082 | assumed | $7.50 | $38,115 |
| SD-FC-LAP · Fiber-cement lap siding from: sidingNetAreaSf | 4,325 sf | 10% · 432.5 | 4,757.5 | 4,757.5 | assumed | $6.50 | $30,923.75 |
| DW-12-4x12 · 1/2" drywall 4x12 sheet from: exteriorWallDrywallSf 4x12 sheet = 48 sf | 90.1 sheet | 10% · 9 | 99.1 | 100 pack-rounded | assumed | $16.50 | $1,635.39 |
| RF-ARCH · Architectural asphalt shingles from: roofAreaSf 1 roofing square = 100 sf | 31.9 square | 10% · 3.2 | 35.1 | 36 pack-rounded | assumed | $125 | $4,390.38 |
| FR-ROOF · Roof framing package from: roofFramingAreaSf | 3,193 sf | 10% · 319.3 | 3,512.3 | 3,512.3 | assumed | $9 | $31,610.70 |
| DW-12-4x12 · 1/2" drywall 4x12 sheet from: ceilingDrywallSf 4x12 sheet = 48 sf | 37.5 sheet | 10% · 3.8 | 41.3 | 42 pack-rounded | derived | $16.50 | $680.63 |
| DW-12-4x12 · 1/2" drywall 4x12 sheet from: partitionDrywallSf 4x12 sheet = 48 sf | 75 sheet | 10% · 7.5 | 82.5 | 83 pack-rounded | assumed | $16.50 | $1,361.25 |
| FR-FLOOR · Floor framing package from: floorFramingAreaSf | 900 sf | 10% · 90 | 990 | 990 | derived | $8 | $7,920 |
| Material planning total | $128,886.21 | ||||||
- openingAreaSf — informational
- envelopeFootprintSf — informational
- exteriorWallPerimeterLf — informational
- exteriorWallLengthLf — informational
- grossExteriorWallAreaSf — informational
- conditionedFloorAreaSf — informational
- This material schedule is not a bid.
- This material schedule is not a purchase order.
- These are the builder's manual planning figures, not supplier pricing.
- The conceptual estimate total and this material planning total are different instruments and are not reconciled.
Distance to the sourced-rate floor
Regeneration history
| Estimate | Configuration | Status | Provenance |
|---|---|---|---|
| 0002 | Managed Lot 008 Mrcldpfy | draft | rev 1 · generated 2026-07-08T21:34:53.115Z |
| 0003 | Managed Lot 009 Mrcldpgw | draft | rev 1 · generated 2026-07-08T21:34:53.177Z |
| 0004 | Managed Lot 010 Mrcldphq | draft | rev 1 · generated 2026-07-08T21:34:53.237Z |
| 0005 | Managed Lot 011 Mrcldpin | draft | rev 1 · generated 2026-07-08T21:34:53.300Z |
| 0006 · viewing | Managed Lot 008 Mrclwrul | draft | rev 1 · generated 2026-07-08T21:45:43.478Z |
| 0007 | Managed Lot 009 Mrclwrvn | draft | rev 1 · generated 2026-07-08T21:45:43.561Z |
| 0008 | Managed Lot 010 Mrclwrwv | draft | rev 1 · generated 2026-07-08T21:45:43.637Z |
| 0009 | Managed Lot 011 Mrclwrxz | draft | rev 1 · generated 2026-07-08T21:45:43.718Z |
| 0010 | Managed Lot 001 Mrez3q54 | superseded | superseded by 0018 at 2026-07-15T22:14:04.914Z |
| 0011 | Managed Lot 002 Mrez3q6k | draft | rev 1 · generated 2026-07-10T13:32:24.644Z |
| 0012 | Managed Lot 003 Mrez3q7u | draft | rev 1 · generated 2026-07-10T13:32:24.790Z |
| 0013 | Managed Lot 004 Mrez3q96 | draft | rev 1 · generated 2026-07-10T13:32:24.939Z |
| 0014 | Managed Lot 005 Mrez3qao | draft | rev 1 · generated 2026-07-10T13:32:25.096Z |
| 0015 | Managed Lot 001 Mrf0p0yq | draft | rev 1 · generated 2026-07-10T14:14:53.795Z |
| 0016 | Managed Lot 002 Mrf0p199 | draft | rev 1 · generated 2026-07-10T14:14:54.154Z |
| 0017 | Managed Lot 003 Mrf0p1jh | draft | rev 1 · generated 2026-07-10T14:14:54.409Z |
| 0018 · active | Managed Lot 001 Mrez3q54 | draft | rev 1 · generated 2026-07-15T22:14:04.914Z |